Delhi - Vadodara _ Pkg-31

Details

Construction of Eight Lane access-controlled expressway starting from Junction with SH-63 near Pratap Nagar Village and ending at Junction with NE-1 near Dodka Vilage of Vadoda District (Ch. 824+920 to 844+382; design Ch. 372+500 to Ch. 391+962) section of Delhi – Vadodara (Pkg 31) Greenfield Alignment (NH-148N) on EPC Mode under Bharatmala Pariyojana in the State of Gujarat

Agreement Date:

05-08-2020

Mode of Bid:

EPC

Time of completion:

24 Months

Awarded/LOA cost

789.4 Crore

Date of Start:

18-05-2021

Employer:

NHAI

Total Length (in KM):

19.462

Tender Cost (in Crore):

801.8

LOA Date:

23-07-2020

Completion Date:

17-05-2023