banner-image

Kanpur Lucknow Expressway (Pkg-2)

Details

Six lane upgradable to Eight lane of Kanpur Lucknow Expressway including spur from Km 28+500 to Km 73+744 in the state of Uttar Pradesh on Hybrid Annuity mode under Bharatmala Pariyojana (Package-2) (the “Project”) on design, build, operate and transfer basis (the “DBOT Annuity” of Hybrid Annuity)

Agreement Date:

12.05.2022

Mode of Bid:

HAM

Time of completion:

30 Months

Awarded/LOA cost

BPC: 1513.00 1st Yr O&M : 3.00 NHAI Price: 1377.55 Crore

Date of Start:

10.11.2022

Employer:

NHAI

Total Length (in KM):

45.244

Tender Cost (in Crore):

1602.95

LOA Date:

15.03.2022

Completion Date:

-