Chakeri - Allahabad

Details

Six Laning of Chakeri Allahabad section of NH-2 (from Km 483.687 to Km 628.753) on HAM mode.

Agreement Date:

25-04-2018

Mode of Bid:

HAM

Time of completion:

30 Months

Awarded/LOA cost

BPC: 2159.00 1st Yr O&M : 8.80 NHAI Price: 1926.93 Crore

Date of Start:

12.01.2019

Employer:

NHAI

Total Length (in KM):

145.066

Tender Cost (in Crore):

1430.16

LOA Date:

13-11-2017

Completion Date:

11.07.2021