Koilwar - Bhojpur (PNC-55%, SPSCPL-45%)

Details

Four Laning of Koilwar to Bhojpur from Km. 137.375 of NH-30 to Km. 27.370 of NH-84 (Design Chainage Km. 33.250 to Km. 77.100) in the State of Bihar under NHDP Phase-III on EPC mode

Agreement Date:

09-09-2015

Mode of Bid:

EPC

Time of completion:

30 Months

Awarded/LOA cost

825.17 Crore

Date of Start:

04-07-2017

Employer:

NHAI

Total Length (in KM):

43.85

Tender Cost (in Crore):

814

LOA Date:

17-08-2015

Completion Date:

03-01-2020