Meerut - Nazibabad Section

Details

53.95 km long Four-laning of Meerut - Nazibabad section of NH-119 (New NH-34) from design chainage Km 11+500 (Meerut) to 39.250 (Behsuma) and from km 79.500 (Bijnor) to 105.700 (Jalalabad) on Hybrid Annuity Mode.

Agreement Date:

31-08-2020

Mode of Bid:

HAM

Time of completion:

24 Months

Awarded/LOA cost

BPC: 1412.00 1st Yr O&M : 3.00 NHAI Price: 1306.54 Crore

Date of Start:

19-03-2021

Employer:

NHAI

Total Length (in KM):

53.95

Tender Cost (in Crore):

1071.31

LOA Date:

23-06-2020

Completion Date:

18-03-2023