banner-image

Aligarh - Kanpur (Pkg-V)

Details

4 laning of Aligarh- Kanpur Section from Km 356.000 (Design chainage Km. 373.085) to Km.414.000 (Design chainage Km.433.728), Package - V, Mitrasen - Kanpur section of NH- 91 on Hybrid Annuity Mode.

Agreement Date:

05-08-2020

Mode of Bid:

HAM

Time of completion:

30 Months

Awarded/LOA cost

BPC: 2052.00 1st Yr O&M : 3.00 NHAI Price: 1859.94 Crore

Date of Start:

15-03-2021

Employer:

NHAI

Total Length (in KM):

60.64

Tender Cost (in Crore):

1621.85

LOA Date:

09-03-2020

Completion Date:

10-09-2023